This function produces a mining schedule for each period scheduled and a summary report for each period.

Function Name:

  • PERIOD REPORT
Fields on the Scheduler report filename form

Report Location Name

Enter the file name to be used to store the report output. Each individual period report is named '"output file name"NNN.not' where NNN is the period number. The summary report is named '"output file name"99999.not'.

Result

sched_db DATABASE     27-May-94           
          Mining Schedule for Period    1           
 SEQU.    BENCH   QUANTITY          TONNES        Au
----------------------------------------------------
    1    475.000  MILL                  15     1.080
                  SKPL                   0      .000
                  WASTE              42702      .000
 
    2    475.000  MILL                4381     2.428
                  SKPL                6524      .922
                  WASTE              82681      .000
 
    3    475.000  MILL                5365     3.207
                  SKPL                7472      .745
                  WASTE              74789      .000
 
    4    475.000  MILL                   0      .000
                  SKPL                 204      .810
                  WASTE              47989      .000
 
    5    470.000  MILL                   0      .000
                  SKPL                   0      .000
                  WASTE              33273      .000
 
----------------------------------------------------
 TOTALS           MILL                9760     2.854
                  SKPL               14201      .828
                  WASTE             281434      .000
----------------------------------------------------